A 12 × 12 ft slab 6 inches thick needs 2.67 cubic yards of concrete — 132 bags of 80-lb mix (or 176 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 264 | — |
| 50 lb · 0.375 ft³ | 212 | — |
| 60 lb · 0.45 ft³ | 176 | $854 |
| 80 lb · 0.6 ft³ | 132 | $783 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 1.56 | 77 | 103 | $457 | $613 |
| 4 in | 1.78 | 88 | 118 | $522 | $655 |
| 5 in | 2.22 | 110 | 147 | $652 | $740 |
| 6 in | 2.67 | 132 | 176 | $783 | $825 |
12 ft × 12 ft = 144 sq ft. Multiply by the thickness in feet (6 ÷ 12 = 0.5 ft) to get 72 cubic feet, and divide by 27 for 2.67 cubic yards.
Adding 10% for uneven ground and spillage gives 79.2 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 79.2 ÷ 0.6 = 132, rounded up to 132 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 3 yd³.
The full method, material data and tips are on the main concrete slab calculator page.