A 4 × 4 ft slab 4 inches thick needs 0.2 cubic yards of concrete — 10 bags of 80-lb mix (or 14 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 20 | — |
| 50 lb · 0.375 ft³ | 16 | — |
| 60 lb · 0.45 ft³ | 14 | $67.90 |
| 80 lb · 0.6 ft³ | 10 | $64.70 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 0.17 | 9 | 12 | $58.23 | $485 |
| 4 in | 0.2 | 10 | 14 | $64.70 | $485 |
| 5 in | 0.25 | 13 | 17 | $84.11 | $485 |
| 6 in | 0.3 | 15 | 20 | $97.05 | $485 |
4 ft × 4 ft = 16 sq ft. Multiply by the thickness in feet (4 ÷ 12 = 0.333 ft) to get 5.33 cubic feet, and divide by 27 for 0.2 cubic yards.
Adding 10% for uneven ground and spillage gives 5.87 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 5.87 ÷ 0.6 = 9.8, rounded up to 10 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 1 yd³.
The full method, material data and tips are on the main concrete slab calculator page.