A new 12×100 ft driveway built as 4 in of #57 stone under 4 in of compacted crusher run takes about 53.4 tons of stone: 22 t of #57 stone and 31.4 t of crusher run, with 10% extra.
“Cheapest” compares bulk delivered with 0.5 cu ft bags at the prices below.
| Layer | Depth | Order | Weight | Bags |
|---|---|---|---|---|
| crusher run | 4 in* | 21.67 cu yd | 31.4 tons | 1,171 |
| #57 stone | 4 in | 16.3 cu yd | 22 tons | 880 |
* finished depth after compaction
Payload is on the Tire & Loading sticker in the driver's door jamb. Single-axle dump trucks carry about 5 tons; bigger orders come on a tandem (up to 18 tons).
Bulk prices are typical 2026 yard and national-guide prices (American Rock Supply, Mulch Pros, Roseville Rock Supply); bag prices are retail snapshots. Tap any price to use your yard's.
| Layer | Depth | Order (cu yd) | Tons | 0.5 cu ft bags | Bulk delivered |
|---|---|---|---|---|---|
| #57 stone | 4 in | 16.3 | 22 | 880 | $1,140 |
| crusher run | 4 in compacted | 21.67 | 31.4 | 1,171 | $1,061 |
The base layer of clean #57 stone drains and spreads the load; the top layer of crusher run has fines that lock together under compaction into a hard driving surface. Penn State's road specification places 8 in loose to finish at 6 in, which is where the 1.33× compaction factor comes from.
At 53.4 tons this job needs more than one tandem load; ask the yard to dump the base stone first, then return with the crusher run once the base is spread and rolled.
The full method, material data and tips are on the main gravel calculator page.