A 10 × 20 ft slab 5 inches thick needs 3.09 cubic yards of concrete — 153 bags of 80-lb mix (or 204 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 306 | — |
| 50 lb · 0.375 ft³ | 245 | — |
| 60 lb · 0.45 ft³ | 204 | $989 |
| 80 lb · 0.6 ft³ | 153 | $907 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 2.16 | 107 | 143 | $635 | $740 |
| 4 in | 2.47 | 123 | 163 | $729 | $783 |
| 5 in | 3.09 | 153 | 204 | $907 | $910 |
| 6 in | 3.7 | 184 | 245 | $1,091 | $918 |
10 ft × 20 ft = 200 sq ft. Multiply by the thickness in feet (5 ÷ 12 = 0.417 ft) to get 83.33 cubic feet, and divide by 27 for 3.09 cubic yards.
Adding 10% for uneven ground and spillage gives 91.67 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 91.67 ÷ 0.6 = 152.8, rounded up to 153 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 3.5 yd³.