A 20 × 20 ft slab 5 inches thick needs 6.17 cubic yards of concrete — 306 bags of 80-lb mix (or 408 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 612 | — |
| 50 lb · 0.375 ft³ | 489 | — |
| 60 lb · 0.45 ft³ | 408 | $1,979 |
| 80 lb · 0.6 ft³ | 306 | $1,815 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 4.32 | 214 | 286 | $1,269 | $1,045 |
| 4 in | 4.94 | 245 | 326 | $1,453 | $1,130 |
| 5 in | 6.17 | 306 | 408 | $1,815 | $1,385 |
| 6 in | 7.41 | 367 | 489 | $2,176 | $1,598 |
20 ft × 20 ft = 400 sq ft. Multiply by the thickness in feet (5 ÷ 12 = 0.417 ft) to get 166.67 cubic feet, and divide by 27 for 6.17 cubic yards.
Adding 10% for uneven ground and spillage gives 183.33 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 183.33 ÷ 0.6 = 305.6, rounded up to 306 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 7 yd³.
The full method, material data and tips are on the main concrete slab calculator page.