4 pads of 30×30×12 in take 0.93 cubic yards of concrete — 46 × 80-lb bags with 10% extra, or 1.25 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 92 | — |
| 50 lb · 0.375 ft³ | 74 | — |
| 60 lb · 0.45 ft³ | 62 | $301 |
| 80 lb · 0.6 ft³ | 46 | $273 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12×12×12 in | 0.15 | 8 | 10 | $51.76 | $485 |
| 18×18×10 in | 0.28 | 14 | 19 | $90.58 | $485 |
| 24×24×12 in | 0.59 | 30 | 40 | $194 | $485 |
| 30×30×12 in | 0.93 | 46 | 62 | $273 | $528 |
30 × 30 × 12 = 10,800 cu in per pad, ÷ 1,728 = 6.25 cu ft. Times 4 pads = 25 cu ft, ÷ 27 = 0.926 yd³.
With 10% extra that is 27.5 cu ft ÷ 0.6 cu ft per 80-lb bag = 45.8, rounded up to 46 bags.
At about $170 per yard plus delivery, fuel and a short-load fee under 4 yd³, a truck beats bags from roughly 3.25 yd³. This job is 1.02 yd³ with waste, so bags make sense — if you have the crew to mix them.