8 pads of 18×18×10 in take 0.56 cubic yards of concrete — 28 × 80-lb bags with 10% extra, or 1 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 55 | — |
| 50 lb · 0.375 ft³ | 44 | — |
| 60 lb · 0.45 ft³ | 37 | $179 |
| 80 lb · 0.6 ft³ | 28 | $181 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12×12×12 in | 0.3 | 15 | 20 | $97.05 | $485 |
| 18×18×10 in | 0.56 | 28 | 37 | $181 | $485 |
| 24×24×12 in | 1.19 | 59 | 79 | $350 | $570 |
| 30×30×12 in | 1.85 | 92 | 123 | $546 | $698 |
18 × 18 × 10 = 3,240 cu in per pad, ÷ 1,728 = 1.875 cu ft. Times 8 pads = 15 cu ft, ÷ 27 = 0.556 yd³.
With 10% extra that is 16.5 cu ft ÷ 0.6 cu ft per 80-lb bag = 27.5, rounded up to 28 bags.
At 0.61 yd³ with waste this is a bag job — a truck's 1 yd minimum plus fees would cost about $485.