9 pads of 12×12×12 in take 0.33 cubic yards of concrete — 17 × 80-lb bags with 10% extra, or 1 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 33 | — |
| 50 lb · 0.375 ft³ | 27 | — |
| 60 lb · 0.45 ft³ | 22 | $107 |
| 80 lb · 0.6 ft³ | 17 | $110 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12×12×12 in | 0.33 | 17 | 22 | $110 | $485 |
| 18×18×10 in | 0.63 | 31 | 42 | $201 | $485 |
| 24×24×12 in | 1.33 | 66 | 88 | $391 | $570 |
| 30×30×12 in | 2.08 | 104 | 138 | $617 | $740 |
12 × 12 × 12 = 1,728 cu in per pad, ÷ 1,728 = 1 cu ft. Times 9 pads = 9 cu ft, ÷ 27 = 0.333 yd³.
With 10% extra that is 9.9 cu ft ÷ 0.6 cu ft per 80-lb bag = 16.5, rounded up to 17 bags.
At 0.37 yd³ with waste this is a bag job — a truck's 1 yd minimum plus fees would cost about $485.
The full method, material data and tips are on the main concrete footing calculator page.