A 12 × 16 ft slab 4 inches thick needs 2.37 cubic yards of concrete — 118 bags of 80-lb mix (or 157 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 235 | — |
| 50 lb · 0.375 ft³ | 188 | — |
| 60 lb · 0.45 ft³ | 157 | $761 |
| 80 lb · 0.6 ft³ | 118 | $700 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 2.07 | 103 | 137 | $611 | $740 |
| 4 in | 2.37 | 118 | 157 | $700 | $783 |
| 5 in | 2.96 | 147 | 196 | $872 | $910 |
| 6 in | 3.56 | 176 | 235 | $1,044 | $875 |
12 ft × 16 ft = 192 sq ft. Multiply by the thickness in feet (4 ÷ 12 = 0.333 ft) to get 64 cubic feet, and divide by 27 for 2.37 cubic yards.
Adding 10% for uneven ground and spillage gives 70.4 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 70.4 ÷ 0.6 = 117.3, rounded up to 118 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 2.75 yd³.