A 16 × 16 ft slab 4 inches thick needs 3.16 cubic yards of concrete — 157 bags of 80-lb mix (or 209 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 313 | — |
| 50 lb · 0.375 ft³ | 251 | — |
| 60 lb · 0.45 ft³ | 209 | $1,014 |
| 80 lb · 0.6 ft³ | 157 | $931 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 2.77 | 137 | 183 | $812 | $868 |
| 4 in | 3.16 | 157 | 209 | $931 | $910 |
| 5 in | 3.95 | 196 | 261 | $1,162 | $960 |
| 6 in | 4.74 | 235 | 313 | $1,394 | $1,088 |
16 ft × 16 ft = 256 sq ft. Multiply by the thickness in feet (4 ÷ 12 = 0.333 ft) to get 85.33 cubic feet, and divide by 27 for 3.16 cubic yards.
Adding 10% for uneven ground and spillage gives 93.87 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 93.87 ÷ 0.6 = 156.4, rounded up to 157 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 3.5 yd³.
The full method, material data and tips are on the main concrete slab calculator page.