A 8 × 10 ft slab 4 inches thick needs 0.99 cubic yards of concrete — 49 bags of 80-lb mix (or 66 × 60-lb), including 10% extra.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 98 | — |
| 50 lb · 0.375 ft³ | 79 | — |
| 60 lb · 0.45 ft³ | 66 | $320 |
| 80 lb · 0.6 ft³ | 49 | $291 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. big-box prices checked October 2026. Tap any price to enter your store's.
| Thickness | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 3.5 in (2×4) | 0.86 | 43 | 58 | $255 | $485 |
| 4 in | 0.99 | 49 | 66 | $291 | $528 |
| 5 in | 1.23 | 62 | 82 | $368 | $570 |
| 6 in | 1.48 | 74 | 98 | $439 | $613 |
8 ft × 10 ft = 80 sq ft. Multiply by the thickness in feet (4 ÷ 12 = 0.333 ft) to get 26.67 cubic feet, and divide by 27 for 0.99 cubic yards.
Adding 10% for uneven ground and spillage gives 29.33 cu ft. Quikrete and Sakrete both rate an 80-lb bag at 0.6 cu ft, so 29.33 ÷ 0.6 = 48.9, rounded up to 49 bags.
Ready-mix is priced at about $170 per yard for 4,000 psi plus delivery, fuel and — under 4 yards — a short-load fee. Plants sell in quarter-yard steps, so the order is 1.25 yd³.
The full method, material data and tips are on the main concrete slab calculator page.