140 ft of 20 × 10 in footing takes 7.2 cubic yards of concrete — 357 × 80-lb bags with 10% extra, or 8 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 713 | — |
| 50 lb · 0.375 ft³ | 571 | — |
| 60 lb · 0.45 ft³ | 476 | $2,309 |
| 80 lb · 0.6 ft³ | 357 | $2,117 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12 × 6 in | 2.59 | 129 | 172 | $765 | $825 |
| 12 × 8 in | 3.46 | 172 | 229 | $1,020 | $875 |
| 16 × 8 in | 4.61 | 229 | 305 | $1,358 | $1,088 |
| 20 × 10 in | 7.2 | 357 | 476 | $2,117 | $1,555 |
| 24 × 12 in | 10.37 | 514 | 685 | $3,048 | $2,345 |
20 in × 10 in = 200 sq in of cross-section, ÷ 144 = 1.389 cu ft per foot. Times 140 ft = 194.44 cu ft, ÷ 27 = 7.202 yd³.
With 10% extra that is 213.89 cu ft ÷ 0.6 cu ft per 80-lb bag = 356.5, rounded up to 357 bags.
At about $170 per yard plus delivery, fuel and a short-load fee under 4 yd³, a truck beats bags from roughly 3.25 yd³. This job is 7.92 yd³ with waste, so order ready-mix.
The full method, material data and tips are on the main concrete footing calculator page.