40 ft of 16 × 8 in footing takes 1.32 cubic yards of concrete — 66 × 80-lb bags with 10% extra, or 1.5 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 131 | — |
| 50 lb · 0.375 ft³ | 105 | — |
| 60 lb · 0.45 ft³ | 87 | $422 |
| 80 lb · 0.6 ft³ | 66 | $391 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12 × 6 in | 0.74 | 37 | 49 | $239 | $485 |
| 12 × 8 in | 0.99 | 49 | 66 | $291 | $528 |
| 16 × 8 in | 1.32 | 66 | 87 | $391 | $570 |
| 20 × 10 in | 2.06 | 102 | 136 | $605 | $740 |
| 24 × 12 in | 2.96 | 147 | 196 | $872 | $910 |
16 in × 8 in = 128 sq in of cross-section, ÷ 144 = 0.889 cu ft per foot. Times 40 ft = 35.56 cu ft, ÷ 27 = 1.317 yd³.
With 10% extra that is 39.11 cu ft ÷ 0.6 cu ft per 80-lb bag = 65.2, rounded up to 66 bags.
At about $170 per yard plus delivery, fuel and a short-load fee under 4 yd³, a truck beats bags from roughly 3.25 yd³. This job is 1.45 yd³ with waste, so bags make sense — if you have the crew to mix them.
The full method, material data and tips are on the main concrete footing calculator page.