20 ft of 12 × 6 in footing takes 0.37 cubic yards of concrete — 19 × 80-lb bags with 10% extra, or 1 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 37 | — |
| 50 lb · 0.375 ft³ | 30 | — |
| 60 lb · 0.45 ft³ | 25 | $121 |
| 80 lb · 0.6 ft³ | 19 | $123 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12 × 6 in | 0.37 | 19 | 25 | $123 | $485 |
| 12 × 8 in | 0.49 | 25 | 33 | $162 | $485 |
| 16 × 8 in | 0.66 | 33 | 44 | $214 | $485 |
| 20 × 10 in | 1.03 | 51 | 68 | $302 | $528 |
| 24 × 12 in | 1.48 | 74 | 98 | $439 | $613 |
12 in × 6 in = 72 sq in of cross-section, ÷ 144 = 0.5 cu ft per foot. Times 20 ft = 10 cu ft, ÷ 27 = 0.37 yd³.
With 10% extra that is 11 cu ft ÷ 0.6 cu ft per 80-lb bag = 18.3, rounded up to 19 bags.
At 0.41 yd³ with waste this is a bag job — a truck's 1 yd minimum plus fees would cost about $485.
The full method, material data and tips are on the main concrete footing calculator page.