80 ft of 16 × 8 in footing takes 2.63 cubic yards of concrete — 131 × 80-lb bags with 10% extra, or 3 yd³ of ready-mix.
| Bag | Bags | Est. cost |
|---|---|---|
| 40 lb · 0.3 ft³ | 261 | — |
| 50 lb · 0.375 ft³ | 209 | — |
| 60 lb · 0.45 ft³ | 174 | $844 |
| 80 lb · 0.6 ft³ | 131 | $777 |
At these prices a truck becomes cheaper from about 3.25 yd³ (147 bags). Over 1–2 yd³, a truck also saves hours of mixing: plan on 3–4 minutes per bag in a mixer.
Typical U.S. prices checked October 2026. Tap any price to enter your store's.
| Size | Cubic yards | 80-lb bags | 60-lb bags | Bag cost | Ready-mix |
|---|---|---|---|---|---|
| 12 × 6 in | 1.48 | 74 | 98 | $439 | $613 |
| 12 × 8 in | 1.98 | 98 | 131 | $581 | $698 |
| 16 × 8 in | 2.63 | 131 | 174 | $777 | $825 |
| 20 × 10 in | 4.12 | 204 | 272 | $1,210 | $1,003 |
| 24 × 12 in | 5.93 | 294 | 392 | $1,743 | $1,343 |
16 in × 8 in = 128 sq in of cross-section, ÷ 144 = 0.889 cu ft per foot. Times 80 ft = 71.11 cu ft, ÷ 27 = 2.634 yd³.
With 10% extra that is 78.22 cu ft ÷ 0.6 cu ft per 80-lb bag = 130.4, rounded up to 131 bags.
At about $170 per yard plus delivery, fuel and a short-load fee under 4 yd³, a truck beats bags from roughly 3.25 yd³. This job is 2.9 yd³ with waste, so bags make sense — if you have the crew to mix them.
The full method, material data and tips are on the main concrete footing calculator page.